- NASA is seeking Phase 1 proposals to design and construct an Aerospace Power Systems Laboratory at Glenn Research Center.
- Written questions are due 12 October; proposals are due 30 October at 1 p.m. Eastern time.
- The stated $45 million figure is a small-business size standard, not a disclosed contract value.
NASA’s Glenn Research Center published a notice on 6 October 2026 inviting Phase 1 proposals for the design and construction of an Aerospace Power Systems Laboratory in Cleveland. NASA describes the principal purpose as a laboratory facility for testing and developing power systems, together with the associated site work, infrastructure and systems.
The notice establishes a short procurement sequence. Written questions are due by 12 October. Proposals are due by 1 p.m. Eastern time on 30 October through NASA’s Enterprise File Sharing and Sync Box. NASA lists 16 December as the anticipated contract-award date and says work would be performed both at Glenn and at the contractor’s facilities.
NASA says the acquisition is a full and open competition under NAICS code 236220, with a $45 million small-business size standard. That figure classifies whether a firm qualifies as small for this procurement; the notice does not identify it as the project budget or contract value. Keeping those meanings separate prevents an administrative threshold from becoming a false cost estimate.
What it means in practice
Dunes Bureau interpretation: the first engineering deliverable for a prospective bidder is a controlled calendar and requirements matrix. The public notice gives milestone dates and a high-level purpose, but a compliant proposal must be built from the official solicitation package and any amendments. Each promised capability should trace to a stated requirement, owner and piece of evidence rather than to an assumption about what a power laboratory ought to contain.
The same discipline applies to interfaces. NASA’s description joins a test facility to site work, infrastructure and supporting systems. A bidder therefore needs to separate the laboratory’s intended function from the utilities, controls, access and construction work that allow it to operate. The 6 October notice does not publish a floor area, contract amount or detailed performance specification, so those points should not be inferred from the announcement or from photographs of existing Glenn facilities.
An invitation is not an award, and an anticipated date is not a completed milestone. The useful follow-up evidence will be formal amendments, the final award and, later, measurable facility capability. Until then, the business development is a live design-and-construction opportunity with a defined timetable—not proof that the proposed laboratory has been funded, built or commissioned.
Sources
NASA Glenn Invites Phase 1 Proposals for Aerospace Power Systems Laboratory — 6 October 2026 ↗
Gary Daines · NASA. Accessed 2026-10-07. NASA factual commercial editorial usage and AI source-disclosure guidelines; third-party exceptions checked.